Scheduled Road Closures – Cherry Street

Cherry Street will experience recurring closures to through traffic on Thursdays and Fridays from November 5 through November 20, 2026, in close coordination with the contractor and local business owners.
Closure Schedule

  • Week 1: Thursday, Nov 5 – Friday, Nov 6
  • Week 2: Thursday, Nov 12 – Friday, Nov 13
  • Week 3: Thursday, Nov 19 – Friday, Nov 20

Project Details

  • Purpose: Safely facilitate lumber deliveries for framing and accelerate underground concrete garage foundation preparation.
  • Coordination: Managed alongside the contractor and local business owners to standardize the schedule and minimize community disruption.
  • Long-term Impact: Once the foundation is complete, contractors will park directly on-site to free up street access.
  • Action Required: Drivers should plan alternate routes on these days to avoid travel delays.

Thank you for your cooperation and understanding.