Cherry Street will experience recurring closures to through traffic on Thursdays and Fridays from November 5 through November 20, 2026, in close coordination with the contractor and local business owners.
Closure Schedule
- Week 1: Thursday, Nov 5 – Friday, Nov 6
- Week 2: Thursday, Nov 12 – Friday, Nov 13
- Week 3: Thursday, Nov 19 – Friday, Nov 20
Project Details
- Purpose: Safely facilitate lumber deliveries for framing and accelerate underground concrete garage foundation preparation.
- Coordination: Managed alongside the contractor and local business owners to standardize the schedule and minimize community disruption.
- Long-term Impact: Once the foundation is complete, contractors will park directly on-site to free up street access.
- Action Required: Drivers should plan alternate routes on these days to avoid travel delays.
Thank you for your cooperation and understanding.