Peco Final Paving Restoration –  Road Closures

PECO completed the installation of the new gas mains in Jenkintown Borough on the Acceleration Gas Infrastructure Modernization Project (AGIMP) project.

PECO’s subcontractor Kehoe Construction, Inc., will return on Monday, April 12th at 7:00 AM to begin the final paving of the affected roads (Runnymede Avenue, Cheltena Avenue and Walnut Street)

Monday, April 12th, Runnymede Avenue (Myrtle to Cloverly) will be closed to through traffic so the roadway can be paved safely. The rest of the week, notifications will be made of the other affected roads that will be closed to through traffic so they too can be safely paved.

The subcontractor has informed all residents affected by this project and will post “NO PARKING” signs as scheduled.

Residents will continue to have access to their driveways but there will be limited access to driveways during paving process. If you do not reside on this road please take another route during these times to avoid disruption of your travels.

All affected roads will be paved from curb to curb the entire length except for Walnut Street which is a State Road. The paving restoration and final paving costs are considered part of this project and are covered by PECO.

If you have any further questions about this project please contact Kehoe Construction at 610-279-0126opens phone dialer or Jenkintown Borough Hall at 215-885-0700.  If you have an emergency dial 911.