Sanitary Sewer Main Project Update Friday, September 25th & Monday, September 28th

The Borough has been notified by the project contractor, National Water Main Cleaning Company, that the Public Sanitary Sewer Main Project will be extended until Monday, September 28th due to equipment failure.

The revised schedule is as follows:

  • Friday- Cedar Street between Summit Avenue and Washington Lane
  • Monday- Mather Road between Wyncote Road and Walnut Street and Walnut Street between Washington Lane and Mather Road

These roads will remain open during this process, however intermittent temporary delays may be expected to allow for life safety of personnel performing the work. Additionally, there will be limited parking in various areas along these roads which will be marked with “temporary no parking” signage.  Please use caution in the area or make plans to take an alternate route to avoid further disruption to your travels. Thank you for your patience and understanding while these necessary improvements are made.

If you have any questions or concerns, please call Borough Hall at (215) 885-0700opens phone dialer. If you have any questions regarding the work being performed please call the National Water Main Cleaning Company Superintendent Chris Orlemann at 973-483-3200opens phone dialer.