Road Closure, Infrastructure Progress and 2017 Road Paving Project.

Today, Monday, August 21st, the Borough’s subcontractor, General Asphalt Paving Co., completed the milling of Shoemaker Avenue and Linda Vista Avenue. General Asphalt will continue milling tomorrow Tuesday, August 22nd at 7:00 AM on Rodman Avenue between Runnymede Avenue and Cloverly Avenue. This will complete the milling of the roads on the 2017 Paving project. The paving of these roads is scheduled to begin Wednesday, August 23rd. Work on this portion of the project is scheduled to end by 4:00 PM each day. During the milling operation residents will have access to their driveways with periodic disruption. During the paving operation residents will not have continuous access to their driveways and will not be able to access their driveway until the paving has cooled for traffic. Continue reading Road Closure, Infrastructure Progress and 2017 Road Paving Project.

Milling & Paving Schedule for Monday August 21

Today PECO’s subcontractor, Kehoe, finished the permanent restoration of the trench on Hillside Avenue from York Road to Walnut Street.

Due to the final permanent restoration being complete, the Borough’s subcontractor, General Asphalt Paving Co., will begin milling this Monday, August 21st at 7:00 AM on Rodman Avenue between Runnymede Avenue and Cloverly Avenue. This work is scheduled to end by 4:00 PM each day. During the milling operation residents will have access to their driveways with periodic disruption.

Additionally, the Borough has been notified that AQUA’s subcontractor, Giuliani, has completed the milling of Washington Lane between York Road and Newbold Road and Township Line Road between Washington Lane and Summit Avenue. Final paving of Washington Lane between York Road and Newbold Road and Township Line Road from Washington Lane to Summit Avenue will begin on Monday August 21st at 7:00 AM.  Residents will not have continuous access to their driveways during the paving operation and will not be able to access their driveway until the paving has cooled for traffic.
Continue reading Milling & Paving Schedule for Monday August 21

Township Line Road work Aug. 18

The Borough has been made aware that AQUA’s subcontractor, Giuliani, has begun the milling operation on Township Line Road between Washington Lane and Summit Avenue today, August 18th, which was a day earlier than originally anticipated. Township Line Road between Washington Lane and Summit Avenue will be closed today until 5:00PM. During the milling operation residents will have access to their driveways with periodic disruption.
Continue reading Township Line Road work Aug. 18

Road Closures & Washington Lane Paving Schedule

The PECO gas main project is nearing completion. PECO’s subcontractor, Kehoe, is performing the final restoration of the trenches. Today the permanent restoration of the trench took place on Shoemaker Avenue between Hillside Avenue and Leedom Street as well as Elm Avenue between Hillside Avenue and Cheltena Avenue. To perform the final restoration safely, Kehoe will be closing Hillside Avenue from York Road to Walnut Street tomorrow, August 18th.

These road closures will last until approximately 4PMContractors will provide access to homes for residents who live in this area.

Additionally,The Borough has been notified that AQUA’s subcontractor, Giuliani, that due to the potential heavy rain in tomorrow’s weather forecast, the paving of Washington Lane between York Road and Newbold Road has been rescheduled to begin Monday August 21st, beginning at 7:00AM. Residents will not have continuous access to their driveways during the paving operation and will not be able to access their driveway until the paving has cooled for traffic.
Continue reading Road Closures & Washington Lane Paving Schedule

Road Closures for Thursday August 17th

The PECO gas main project is nearing completion. PECO’s subcontractor, Kehoe, is performing the final restoration of the trenches. Today the permanent restoration of the trench took place on Rodman Avenue from Myrtle Avenue to Walnut Street and Linda Vista Avenue between Runnymede Avenue and Cheltena Avenue. To perform the final restoration safely, Kehoe will be closing Shoemaker Avenue between Hillside Avenue and Leedom Street as well as Elm Avenue between Hillside Avenue and Cheltena Avenue tomorrow, August 17th.

These road closures will last until approximately 4PMContractors will provide access to homes for residents who live in this area.

Additionally,The Borough has been notified that AQUA’s subcontractor, Giuliani, had completed the milling of Washington Lane between York Road and Newbold Road today. Tomorrow. August 17th, Washington Lane between Greenwood Avenue and Newbold Road will be closed to allow for the preparation and the start of the paving of Washington Lane. This road closure will last until approximately 5:00PM.
Continue reading Road Closures for Thursday August 17th