Today, Monday, August 21st, the Borough’s subcontractor, General Asphalt Paving Co., completed the milling of Shoemaker Avenue and Linda Vista Avenue. General Asphalt will continue milling tomorrow Tuesday, August 22nd at 7:00 AM on Rodman Avenue between Runnymede Avenue and Cloverly Avenue. This will complete the milling of the roads on the 2017 Paving project. The paving of these roads is scheduled to begin Wednesday, August 23rd. Work on this portion of the project is scheduled to end by 4:00 PM each day. During the milling operation residents will have access to their driveways with periodic disruption. During the paving operation residents will not have continuous access to their driveways and will not be able to access their driveway until the paving has cooled for traffic.
PECO’s trench restoration Contractor, Kehoe has completed all trench restoration on the West side of Town (Hillside Avenue, Elm Avenue, Leedom Street, Cedar Street, Maple Street and Cloverly Avenue.) . The PECO gas main project is continuing on the East side of town. This work on (Rydal Road, Clement and Vernon Roads.) Once the gas mains and laterals are complete on the East side of town, permanent trench restoration will be performed there as well.
Additionally, Aqua’s Contractor, Giuliani, completed final paving of Washington Lane between York Road and Newbold Road and are scheduled the pave Township Line Road tomorrow between Washington lane and Summit Avenue.
Please make plans to take an alternate route to avoid further disruption to your travels. Thank you for your patience and understanding while these necessary improvements are made.
If you have any questions or concerns please do not hesitate to get in contact with the Borough at (215) 885-0700