2019 Paving Project Progress Update

2019 PAVING PROJECT PROGRESS UPDATE – All milling and paving on this project was successfully completed today.

The entire project is expected to be completed by days end tomorrow. The Borough has negotiated a joint municipal agreement with Abington Township to have the thermoplastic traffic control striping installed at a savings to the Jenkintown Borough tax payers. That traffic control striping (school zones, cross walks, stop bars, etc.) is being installed this afternoon and early evening. Read More »

AQUA Pennsylvania Water Main Replacement Update

AQUA’s sub contractor, Caddick Utilities, will continue the excavation and watermain installation on Vernon Road tomorrow, September 12, 2019. Vernon Road will be closed to “thru Traffic” from 7:00 AM – 3:00 PM between Homestead Road and Vista Road to allow for the roadway to be excavated and the new watermain to be safely installed.  During this process, residents on Vernon Road will continue to have access to their properties. If you do not reside on one of these streets please plan to take another route during these times to avoid disruption to your travels
Read More »

AQUA Pennsylvania Water Main Replacement- Phase two

AQUA’s sub contractor, Caddick Utilities, has completed the watermain installation today on Homestead Road between Newbold and Vernon Roads.  Tomorrow, September 11, 2019, Vernon Road will be closed to “thru Traffic” from 7:00 AM – 3:00 PM between Homestead Road and Vista Road to allow for this portion of the roadway to be excavated and the new watermain safely installed.  During this process, residents on Vernon Road will continue to have access to their properties. Read More »

2019 Paving Project Began Today

2019 PAVING PROJECT UPDATE – The paving project began this morning and is on schedule to be completed this week. Walnut Street and Cedar Street were milled today and had the sub-base inspected by the Borough Engineer. The Contractor’s work schedule for tomorrow includes; placement of leveling course paving on the milled areas of Walnut and Cedar Streets, milling of Highland Avenue (after the start of the school day) and final paving of Cedar Street. The final paving of Walnut Street and Highland Avenue are tentatively scheduled for Wednesday, September 11th.
Read More »

The owner of this website has made a commitment to accessibility and inclusion, please report any problems that you encounter using the contact form on this website. This site uses the WP ADA Compliance Check plugin to enhance accessibility.