The demolition project at 610 Summit Avenue is proceeding as planned and on schedule. The demolition of the Life Center portion of the project has commenced. The Borough Engineer, JPD and Borough Administration met with Roizman Development Inc. and the Demolition Contractor for Summit House Associates LLC. to discuss the progress and future demolition schedule.
The current demolition schedule is as follows: Life Center demolition has commenced. As of today, Monday, March 11th, the demolition Contractor will continue with the demolition of the Life Center using mechanical equipment. Friday, March 15th, the demolition of the shared party wall with Borough hall, will be performed by hand only, for safety and to minimize potential damage to Borough property.
On Monday, March 25th, Borough hall will be closed so the demolition of the shared party wall can be safely completed. The JPD has provided a statement (shown below in blue) that will be issued under separate cover as well.
On Monday, March 25th, from 7am to 4pm the Police Department will not be open for walk in customer service, due to construction and demolition, of the party wall between the Borough building and Salem Church. Patrol and calls for service will not be affected. If you need to speak to an officer call 215-884-1200 or if an emergency call 911.
Thank you.
Albert J. DiValentino, Chief of Police
Jenkintown Police Department
700 Summit Ave.
Jenkintown PA 19046
(215) 884-1202
ADiValentino@JenkintownPD.orgcreate new email
Thank you all and apologies for any inconvenience this may cause. Should you have any questions please contact, Borough Hall at (215) 885-0700.